Modern locks for the world's busiest artificial shipping lane

25 Mar 2022

With the passage of 90 ships each day, the Kiel Canal in Germany is a key element of the trans-European transport network. Our experts are planning the modernization of the Kiel-Holtenau locks during ongoing operation.

As the busiest artificial sea route in the world, the 98-km Kiel Canal plays an important role in freight traffic. It has connected the North Sea and the Baltic Sea since the end of the 19th century, and now averages 90 ships a day and 100 million tons of goods per year.

One of two approaches to the canal is the Kiel-Holtenau lock. It consists of two locks. Currently, only the larger lock (310 m long by 42 m wide) is operational, as the smaller one is under construction. But there is also a need to modernize the large lock.

The Kiel Canal Construction Authority commissioned our experts from Tractebel Hydroprojekt in Magdeburg, Germany to plan a new sluice drive variant to be used for the entire lock system. The task is to develop a new drive by the end of 2025 that is reliable, fail-safe and low-maintenance. The concept will provide for two drives for each lock gate so that replacements are available at all times in the event of a malfunction.

New sluice drives will improve the entire lock system

Preliminary investigations during operation

For the planning phase, our experts examined the specifications of the existing plant dating from 1967 and compared them with measurement data from ongoing operations. The findings form the basis for further planning steps.

A main challenge during these preliminary investigations is to keep the lock operational with minimal downtime. To accomplish this, our experts called on measurement specialist Althen Sensors & Controls. Althen developed and carried out project-specific individual measurement solutions to determine, for example, exact load peaks. These real measured values serve as a basis for precisely dimensioning the new sluice drives and identifying and eliminating any problems that may arise during the planning phase.

Our experts are currently drawing up the approval documents for the construction phase. They will then prepare the tender documents and advise the client throughout the Europe-wide bidding process.

The Kiel Canal, the busiest artificial sea route in the world

"A smoothly functioning waterway between the North Sea and the Baltic Sea means shorter and therefore more environmentally friendly transport routes. We are planning a modern, durable, energy-efficient and fail-safe operation that uses eco-responsible lubricants and can perform its task reliably and effectively."

Tobias Schaulat, project engineer

Discover our hydraulic infrastructure solutions

 

Related news

Doel

Supporting the Belgian nuclear operator in managing radioactive waste safely

Jointly with the Belgian nuclear operator, ENGIE Electrabel, Tractebel has completed the filling of the first High Integrity Container (HIC) as part of the project...

Find out more
23 Apr 2025
AdobeStock_410620092

Our 2024 neutralization plan

At Tractebel, our goal is to reduce our absolute emissions by more than 5% annually. 

Find out more
21 Apr 2025
RAT-rover-by-night

Advancing nuclear-fueled thermoelectric generator technologies for space exploration

The EU-funded STARTREC project aims to develop advanced thermoelectric generators for space exploration and other applications, such as industrial and domestic use. As a...

Find out more
17 Apr 2025
vsm6_almost_there_2_small

Fusion energy: leveraging our nuclear expertise for ITER

For 11 years, our nuclear experts have contributed to the International Thermonuclear Experimental Reactor (ITER), a groundbreaking energy project involving 35 countries...

Find out more
06 Mar 2025