Services provided
Pre-Feasibility Study
- Technology evaluation and selection for H2 and NH3 production
- Optimization studies balancing PV - Wind Farm – Grid (PPA Green), Electrolyser and Continuous H2 supply
- Definition of the optimal configuration.
- Basis of design, PFD, HMB, Layout, technical specifications
- CAPEX/OPEX estimation.
- Calculation of the LCOH / LCOA
- Local framework analysis
- Legal & permitting analysis
NH3 PIPELINE TECHNICAL OVERVIEW
- 10’’ diameter
- 20km length
- 27barg operating pressure
- 12barg pressure drop
- 154ton/h maximum operating flowrate