Snowy 2.0: A pumped-storage plant of colossal proportions

20 Jul 2022

The expansion phase of the 4,100-MW Snowy Mountain hydroelectric scheme is currently underway with the Snowy 2.0 project. Our hydropower experts are working through the numerous and highly complex detailed design and working design studies of this landmark pumped-storage power plant.

The iconic Snowy Mountain hydroelectric and irrigation scheme, originally built from 1949 through 1974, is Australia's biggest renewable energy project. Snowy 2.0, the highly technical extension of this project led by public company Snowy Hydro Limited, has been in full swing since 2019. As design consortium leader, our experts are finding innovative ways to tackle this extremely large and uniquely challenging project.

A project of colossal proportions

The Snowy 2.0 expansion involves the construction of a 2,000-MW underground pumped-storage hydroelectric power plant that will link two existing water reservoirs. The project features 27 km of tunnels – waterways, auxiliary and access tunnels - and an underground power station measuring 22 m wide, 50 m high, 250 m long and located beneath around 750 m of solid rock.

Snowy 2.0 : long section (not to scale)
Snowy 2.0 expansion: A cross-section of the 27-km underground tunnel and power station (not to scale)
 
The deep complexities of Snowy 2.0
Patrick Lignier

 

“The underground caverns – the machine hall (main) and the transformer hall – are extremely complex from a technical perspective because of their size and the in-situ constraints which are comparable to the rock strength,” explains Patrick Lignier, Technical Director at Tractebel. “The constraints released by the excavation work are redistributed around the caverns, resulting in local weakening of the rock – plasticization – and a distortion towards the cavern interior.

The infrastructure is kept stable by a series of passive anchors – 23,000 in total - injected along the entire length, and projected fibre-reinforced concrete which behaves like a skin over the cavern wall. Significant precautions have been taken to ensure that the covering is built to last: the anchors are doubly protected against corrosion,” says Lignier.

Another major challenge is the fact that there is no technical reference framework or sizing standard for this type of infrastructure, which is under a heavy load. World-renowned experts and other specialists engaged in intense technical discussions to develop a design that will ensure the infrastructure has a service life of at least 150 years. These discussions were based on complex three-dimensional calculations modelling all of the underground infrastructure, the main geological discontinuities, the excavation phases and the installation of the anchors.

Key figures

Main hall: Height: 50 m - Width: 32 m - Length: 250 m - Anchors: 15,000
Transformer cavern: Height: 46 m - Width: 20 m - Length: 220 m - Anchors: 8,000

SNOWY 2.0 : models 3D, 2D, BIM
3D Model: Global stability  2D model: Rock support design Unwedge Model: Block Stability BIM model
 
Tractebel in close collaboration with stakeholders

As engineering consortium lead, our hydropower experts are working closely with partners Lombardi (tunnels) and Coffey (surface infrastructures), as well as contracting authority Snowy Hydro Limited, Engineering, Procurement and Construction (EPC) contractor Future Generation Joint Venture consortium (WeBuild, Clough, Lane), and equipment manufacturer Voith.

1.500+ drawings

The preliminary design (Level 1) was delivered and approved in 2021. The detailed design (Level 2) is currently underway and will be submitted in 2022. The detailed design, the basis for the construction works, requires an extremely high level of detail, and generates a significant quantity of calculations and plans. Altogether, more than 1,500 plans will be delivered, and hundreds of interfaces will be resolved with the equipment manufacturer.

2021 saw intense work carried out and operations rigorously coordinated with equipment manufacturer Voith, for which the project team went to great lengths to collect input data. Processing the critical interfaces made it possible to define the baseline of the detailed design for the civil engineering of the power station complex.

A major technical accomplishment

The Snowy 2.0 project will be a major technical milestone – both in terms of its size and its level of technical difficulty. It is Australia's largest renewable energy project, and one of biggest pumped-storage projects in the world. It has also been an opportunity for Tractebel to bolster its position as a global hydropower leader in engineering services delivered to contractors.

Watch SNOWY HYDRO’s video to find out more about Snowy 2.0
https://www.youtube.com/watch?v=TJOFiN8Nw5o&list=PLLrLa65bPqJFUlvwxg7H9mcXmjffOU_sH 

Discover our Hydropower solutions

 

 

Related news

Vue_aerienne_du_CNPE_du_Blayais_2024_YohanEspiaube_copyrights_YohanEspiaube

Completing first-of a-kind intervention: Blayais nuclear reactor’s primary elbow replacement in France

Tractebel contributes to upgrading the French nuclear fleet, which provides over 70% of France’s low-carbon electricity, to extend its lifetime beyond 40 years. Jointly with...

Find out more
12 Nov 2024
Nuclear_Electric_Propulsion_tug_illustration_Copyrights_ESA_credits

Tractebel-led consortium completes ESA RocketRoll project on Nuclear Electric Propulsion for space exploration

The consortium has defined a comprehensive technology roadmap to equip Europe with advanced propulsion systems capable of undertaking long-duration missions, including...

Find out more
31 Oct 2024
Green-Turtle-Tractebel

Colossal battery park in Belgium to store energy to power 385,000 households 

Green Turtle battery park, among...

Find out more
30 Sep 2024
Princess-Elisabeth-Energy-Island

World’s first energy island takes shape in Belgium’s North Sea

The Princess Elisabeth Energy island, under construction 45 km off the coast, will centralize and deliver up to 3.5 GW of electricity from nearby wind farms back to...

Find out more
30 Sep 2024