Tehri Pumped Storage Project

  • Owner Engineer
Client
Tehri HDC (Tehri Hydro Development Corporation)
Country
India
Period
2007 – 2025
Matthieu Beraud
Head of Water
Kontakt aufnehmen
Erbrachte Dienstleistungen
  • Technical & regulatory consultancy
  • Owner's or Lender's Engineer

The Challenge

Implement an underground 4×250 MW PSP with exceptional head range (≈130–230 m) using existing reservoirs and previously built works.

The Solution

Tractebel provided end-to-end technical support for the Tehri PSP project. This included the preparation and submission of complete pre-qualification and tender documents for the EPC contract, assistance with bid clarifications, evaluation of offers, and contract award. During the execution phase, Tractebel reviewed designs, studies, and drawings, ensuring compliance and quality up to commissioning. The project also included training and knowledge transfer to local stakeholders, reinforcing long-term operational capacity.

The Impact

Progress toward safe commissioning of a highly flexible storage plant serving India’s grid.

Digitale Apps

Gestalten Sie Ihre Wirkung neu mit unseren digitalen Lösungen

Referenzen

Unser Beitrag in Wasser

Alle Referenzen